Construction of Jetties and Allied Infrastructure. Of the 8 notified landing sites on the coast, jetties and allied infrastructure are being constructed at 5 sites (2 by the GDA and 3 by the BCDA). The GoB has consequently requested GLLSP II to assist on the remaining 3 priority sites which are currently under technical feasibility study by GLLSP I, to be completed by March 2020. Once the feasibility study becomes available, the PMU will initiate the procurement process for detailed design and construction. The construction will be done in two phases: (i) first the jetties and break-water will be constructed, to be finalized by the end of year two of GLLSP II. As soon as work on jetties starts, the allied infrastructure will be designed /customized per site, based on the need of the fisherfolks, and construction initiated.